Bragin, Gomel Region, Belarus

Description of the project

The construction of a 4.2 MWp solar power station in Bragin (the Republic of Belarus) at the site of decontamination of equipment that took part in the liquidation of the consequences of the Chernobyl accident is the first project of the Consortium RODINA-ENERPARC AG in the exclusion zone.
This project was the first step in implementing the Consortium's multi-year strategy for the construction of a number of Solar Power Plants in the territories affected by the Chernobyl accident. The construction period was 50 days and was successfully completed in August 2016.
Download presentation of the project
Bragin

Specifications

Rated power: 4.2 MWp
Annual capacity: 4 519 MWh per year
Term of the construction project: 50 days
Installed by Solar Modules: 15 876
Inverter efficiency: 98.7%
The value of the “green tariff”: 0.32 USD kWh
Payback period: < 5 years
Date of implementation: August 2016